Public building sites: the State owes contractors the price rises on 2025 works. The ministry looks for the money by postponing tomorrow's railways
15 November 2026, 16:13
On 13 November in Rome, the builders' association Ance presented the bill to the Infrastructure Minister. When a firm builds a school or a road for a public body, the price is the one set in the tender; if cement, steel and asphalt then rise in price, procurement rules grant it compensation, paid from a State fund. For work carried out in 2025, the compensation still to be paid is worth €1.8 billion, and a similar amount is estimated for 2026. The minister announced that the Infrastructure decree will cover €371 million of it, to settle the first half of last year, and admitted: "at least a billion is still missing", to be requested from Parliament through the budget law, because "this is work already done". The materials, in other words, are already in the walls and under the road surface; the price rise, for now, has been paid by whoever bought them.
To find that billion, the ministry also has an idea of its own: take the money from some railway works that have yet to start and use it for those already under way, in other words "rescheduling some railway investments". So the price rises on work already done are paid for by postponing projects that, when they do start, will cost even more. The railways, after all, already put few new works out to tender: in 2025 tenders from Rfi, the state-owned company that runs the network, fell by 90 per cent.
The problem is not only the builders'. The association that represents them has put a number on the minister's "at least": €1.4 billion is needed right away, otherwise around 13,000 building sites risk stopping. Almost six in ten belong to municipalities, provinces and regions: schools, roads, flood defences, neighbourhoods to be regenerated. Between 2025 and 2026 the compensation for material price rises is worth around €3.6 billion in total, and taxpayers will pay it in any case, because the works are public. The only question is how long firms, especially the smallest ones, can advance it out of their own pockets, paying suppliers and workers with money the State admits it owes and cannot say when it will pay.
The bill arrives just as local authorities are about to have less money to invest. According to government forecasts cited by the builders, between 2026 and 2029 investment resources for local authorities will fall by almost a quarter, while those of ministries and other central bodies will grow by about a fifth. Municipalities, provinces and regions, which own most of the sites at risk, will therefore have less money to open new ones; ministries will have more, and meanwhile the Infrastructure Ministry still has to settle last year's works.
The 2025 works are done and waiting for the balance; the railway works that were due to start later, if the ministry finds the missing money there, will begin later still.
This article was prompted by a news item published in Milano Finanza on 13 November 2026.